Project Details
ASU Concho Hall Demolition
| Project #: | 23-07 |
| Detailed Status: | Project Closed |
| Campus: | ASU San Angelo |
| Location: | 2601 W. Avenue N |
| Budget | |
| Board Approved Budget: | $6,360,000 |
| Adjusted Budget: | $6,360,000 |
| Final Cost: | $4,865,858 |
| Schedule | |
| Construction Start Date: | 02.01.2024 |
| Project Completion: | 11.29.2024 |
| Project Team | |
| Program Director: | Jeff Sutherland |
| Contractor: | Collier Construction |
| Design Professionals: | R2M |
| CM Agent: | N/A |
| Description | |
| The project will demolish the existing 10-story Concho Hall Residence building that was constructed in 1969 and contains 99,483 GSF. | |